明慧

格尔木的太阳落得晚。下午六点,光伏板还在一板一眼地追着光转,远处昆仑山的雪线泛白,戈壁上的风把塔拉滩的沙吹成一道薄雾。这里的人习惯把"光"和"风"当成两种农时——什么时候发电多,什么时候要弃,心里都有本账。

这座位于柴达木盆地南缘的城市,正在把这两种"农时"装进同一张网里。海西州的风光资源在青海省内居于前列,格尔木周边集中布局了大规模光伏与风电基地,配套的储能、汇集站、外送通道陆续建成。随着新能源装机占比抬高,电网的运行逻辑也在改变:过去是"跟着负荷发电",现在是“跟着天气调度”。

变化最直观的地方在调度曲线。中午光伏出力上来,本地负荷吃不下,外送通道又受断面限制,弃光压力就出现了;傍晚光伏退去、用电高峰上来,需要其他电源快速顶上。这条"中午鼓包、傍晚塌陷"的曲线,是每一个高比例新能源地区都要面对的技术难题。

储能是填这道沟的第一种工具。青海在独立储能与共享储能上的探索起步较早,格尔木周边的储能电站以磷酸铁锂为主,部分项目开始尝试更长时长的技术路线。储能的收益模式也在演变:从早期的“配建”义务,逐步转向容量租赁、现货价差套利、辅助服务补偿并存的组合。

光热是格尔木另一张牌。熔盐塔式光热电站自带大规模储热能力,白天把热量存在熔盐罐里,晚上放出来继续发电,出力曲线比光伏平滑得多。这类项目在青海已有投产案例,技术上的价值不只在发电量,更在于它提供了一种“可调度的太阳能”,对电网而言,可控性比装机规模更珍贵。

多能互补是青海这几年的主线思路。把光伏、风电、水电、光热、储能打包成一个电源群,通过统一的协调控制对外呈现一条相对平稳的出力曲线,再通过特高压通道外送。格尔木所在的柴达木盆地,正是这类基地的重要落点。技术难点在协调控制:不同电源的响应速度差了几个数量级,水电机组调得快,光热有热惯性,储能几乎瞬时响应,如何让它们在同一个指令下协同动作,需要一套精细的控制策略与预测系统。

外送通道的能力,决定了本地新能源的天花板。青海的清洁能源外送依托特高压直流工程,通道的输送曲线要与受端电网的负荷特性匹配。中午送得多、晚上送得少,受端未必接受;要提升通道利用率,就得靠储能与光热把中午的电“搬”到晚上,这在技术上可行,在 economics 上取决于价差。

电价机制是最现实的一道坎。新能源全面参与市场交易之后,中午时段的电价被压得很低,储能充电成本下降,套利空间本应扩大;但峰谷价差能否稳定、辅助服务的补偿标准如何定,直接决定储能项目的现金流。对格尔木这样的资源富集区,本地消纳空间有限,电价信号更多来自外送与省内市场的叠加,机制设计的复杂度更高。

产业消纳是另一条路。格尔木把新能源优势往产业链下游延伸,引进高载能的绿色制造项目,用绿电就近消纳替代远距离输送。这类项目的选址逻辑与传统工业不同:过去看煤、看矿、看运输,现在先看绿电的可获得性与价格。绿氢、绿色甲醇、绿氨等方向在柴达木盆地被反复讨论,核心约束仍是成本——电解槽的利用小时数、绿电价格、储运环节的损耗,三者决定了产品能不能卖出去。

生态约束始终在场。柴达木盆地生态脆弱,光伏阵列的占地、施工期的扰动、组件清洗的用水,都需要精细管理。格尔木的光伏基地普遍采用支架抬高、板下植被恢复的做法,牧场与光伏共存的模式在部分项目上试点。这类做法的价值不只是环评过关,还在于减少清洗频次、降低风蚀,属于工程与生态的双向优化。

沙尘是对设备的长期考验。戈壁的沙尘天气频繁,组件表面的积灰会拉低发电效率,逆变器、箱变的散热风道也容易被堵。运维策略因此与东部地区不同:清洗周期要按沙尘过程动态调整,设备选型要更看重防护等级,备件储备要考虑运输距离。这些细节不写进技术方案,却实实在在影响发电量。

电网的调节资源也在增加。除了储能与光热,火电灵活性改造、需求侧响应、电动汽车充电的时序管理都被纳入调节池。格尔木的负荷基数小,工业负荷的可调节部分有限,需求侧响应的空间不如东部城市,调节能力仍要靠电源侧解决。这也是资源型城市在新型电力系统建设中的共性难题。

从城市的角度看,能源转型带来的不只是电源结构的变化。格尔木的城市供热、公共交通、工业园区用能,都在往电气化方向走。高原地区的采暖季长,电采暖的负荷增长对配电网是压力,也提供了消纳新能源的窗口——把采暖负荷与光伏出力对齐,削峰填谷的效果比单纯建储能更经济。

人才与运维体系是容易被忽略的一环。大规模新能源基地需要大量的运行、检修、数据分析人员,格尔木的人口规模有限,多数技术岗位要从外地引进。这几年当地与职业院校合作培养本地运维力量,把光伏电站的日常巡检、组件更换、数据监控做成可本地化的技能岗位,这类工作的稳定性比项目本身更长久。

傍晚的风起来了。光伏出力掉到零,储能电站开始放电,光热的熔盐泵启动,汽轮机的声音在戈壁上显得很轻。调度屏幕上的曲线被一点点填平,这就是这座高原城市每天要完成的一次平衡。

绿证与绿电交易是格尔木正在补的另一课。资源富集区的企业用绿电生产,产品出口时要用凭证证明电力来源,这让绿电交易从政策要求变成了市场刚需。交易机制的关键在溯源:电从哪座电站来、什么时段发的、有没有重复计算,需要区块链、计量、结算三套系统的配合。对资源型城市而言,把绿电的环境价值卖出去,比多发几亿度电更能改变收益结构。

(来源:中国能源产业发展网相关报道;青海省能源局公开信息;国网青海省电力公司公开资料)

【研究支持机构:《中国工业报社》能源与双碳研究中心 |中国能源产业发展网】

Minghui

The sun sets late in Golmud. At six in the afternoon, the photovoltaic panels are still methodically following the light, and the snow line on the distant Kunlun Mountains looks pale. The wind on the Gobi blows the sand of the Talatan into a thin mist. People here are used to treating "light" and "wind" as two types of farming seasons—when to produce more electricity, when to abandon it, they all have it figured out in their minds.

This city, located on the southern edge of the Qaidam Basin, is putting these two "farming seasons" into the same grid. The wind and solar resources of Haixi Prefecture rank among the top in Qinghai Province, with large-scale photovoltaic and wind power bases concentrated around Golmud, and the supporting energy storage, collection stations, and transmission channels being built one after another. With the rising proportion of renewable energy installed capacity, the operation logic of the power grid is also changing: in the past, it was "generating according to the load," now it is "dispatching according to the weather."

The most intuitive changes are seen in the dispatch curve. At noon, photovoltaic output rises, local demand can’t absorb it all, and the outbound transmission channels are limited, creating pressure to curtail solar power; in the evening, as solar power declines and electricity demand peaks, other power sources need to ramp up quickly. This 'bulge at noon, dip in the evening' curve is a technical challenge that every region with a high proportion of renewable energy has to face.

Energy storage is the first tool to fill this gap. Qinghai started early in exploring both independent and shared energy storage. Around Golmud, energy storage power stations mainly use lithium iron phosphate, with some projects beginning to try longer-duration technologies. The revenue model for energy storage is also evolving: from the early obligation of 'matching construction,' it is gradually shifting to a combination of capacity leasing, spot price arbitrage, and compensation for ancillary services.

Solar thermal energy is another card for Golmud. Molten salt tower solar thermal power plants come with large-scale thermal storage capacity. During the day, they store heat in molten salt tanks, and at night, they release it to continue generating electricity, producing a power output curve that is much smoother than that of photovoltaic power. Such projects have already been put into operation in Qinghai. Their technical value lies not only in power generation but also in providing a form of 'dispatchable solar energy,' which is more valuable to the grid for its controllability than for installed capacity.

Multi-energy complementarity has been the main approach in Qinghai in recent years. By combining photovoltaic, wind, hydro, solar thermal, and energy storage into a single power cluster, and presenting a relatively stable output curve externally through unified coordinated control, the power is then transmitted via UHV (ultra-high voltage) channels. The Qaidam Basin, where Golmud is located, is an important site for such bases. The technical difficulty lies in coordinated control: different power sources have response speeds that differ by several orders of magnitude. Hydropower units can adjust quickly, solar thermal has thermal inertia, and energy storage responds almost instantaneously. How to get them to operate in coordination under the same command requires a sophisticated control strategy and forecasting system.

The capacity of the delivery channel determines the ceiling for local renewable energy. Qinghai's clean energy delivery relies on UHVDC projects, and the transmission curve of the channel must match the load characteristics of the receiving-end grid. Delivering a lot at noon and little in the evening may not be acceptable to the receiving end; to improve channel utilization, energy storage and concentrating solar power are needed to 'move' the electricity from noon to the evening. Technically this is feasible, but economically it depends on price differences.

The electricity price mechanism is the most practical hurdle. After renewable energy fully participates in market trading, electricity prices during midday are depressed, lowering the cost of charging storage and theoretically expanding arbitrage opportunities. However, whether peak-valley price differences remain stable and how compensation standards for auxiliary services are set directly determine the cash flow of storage projects. In resource-abundant areas like Golmud, local consumption space is limited, and electricity price signals mainly come from the combination of external delivery and intra-provincial markets, making mechanism design even more complex.

Industrial consumption is another path. Golmud extends its renewable energy advantages downstream in the industrial chain, introducing high-energy-density green manufacturing projects, using green electricity locally instead of transmitting it over long distances. The site selection logic for these projects differs from traditional industries: in the past, choices were based on coal, minerals, and transportation, but now the availability and price of green electricity come first. Directions such as green hydrogen, green methanol, and green ammonia have been repeatedly discussed in the Qaidam Basin, with the core constraint still being cost — the utilization hours of electrolyzers, the price of green electricity, and losses in storage and transportation, as these three factors determine whether the products can be sold.

Ecological constraints are always present. The Qaidam Basin is ecologically fragile, so the land occupied by photovoltaic arrays, the disturbances during construction, and the water used for cleaning components all require careful management. Photovoltaic bases in Golmud generally use raised racks and restore vegetation under the panels, and some projects are piloting a model of coexistence between pastures and photovoltaics. The value of these practices is not just in passing environmental assessments but also in reducing cleaning frequency and lowering wind erosion, representing a two-way optimization of engineering and ecology.

Dust is a long-term test for equipment. In the Gobi Desert, sand and dust weather is frequent, and dust accumulation on component surfaces can reduce power generation efficiency, while the cooling pathways of inverters and box transformers are also easily blocked. Therefore, operation and maintenance strategies differ from those in eastern regions: cleaning cycles need to be dynamically adjusted according to dust events, equipment selection must pay more attention to protection ratings, and spare parts reserves must consider transportation distance. These details are not written into technical plans, yet they have a real impact on power generation.

The grid's regulation resources are also increasing. In addition to energy storage and concentrated solar power, flexibility upgrades of thermal power, demand-side response, and the timing management of electric vehicle charging are included in the regulation pool. The load base in Golmud is small, and the adjustable portion of industrial load is limited, so the potential for demand-side response is not as large as in eastern cities, meaning regulation capability still needs to be addressed on the supply side. This is also a common challenge for resource-based cities in the construction of the new-type power system.

From the perspective of the city, the energy transition brings more than just changes in the power generation structure. Urban heating, public transportation, and energy use in industrial parks in Golmud are all moving toward electrification. The heating season in the plateau region is long, and the increasing load from electric heating puts pressure on the distribution grid, but it also provides a window for absorbing renewable energy—aligning the heating load with photovoltaic output is more cost-effective for peak shaving and valley filling than simply building energy storage.

Talent and operation & maintenance systems are aspects that are easily overlooked. Large-scale renewable energy bases require a large number of operation, maintenance, and data analysis personnel. Golmud has a limited population, so most technical positions need to be filled by people from outside. In recent years, local cooperation with vocational schools has been developed to cultivate local O&M personnel, making daily inspections, component replacements, and data monitoring of photovoltaic power stations into skills that can be localized. The stability of these jobs lasts longer than the projects themselves.

The evening wind rises. Photovoltaic output drops to zero, the energy storage stations begin discharging, the molten salt pumps of the solar thermal stations start, and the sound of the turbine seems very soft on the Gobi. The curves on the dispatch screen gradually level out—this is the balance that this plateau city has to achieve every day.

Green certificates and green electricity trading are another lesson that Golmud is currently making up. Companies in resource-rich areas use green electricity for production, and when exporting products, they need certificates to prove the source of the electricity. This turns green electricity trading from a policy requirement into a market necessity. The key to the trading mechanism lies in traceability: from which power station the electricity comes, at what time it was generated, and whether it has been counted more than once. This requires the collaboration of three systems: blockchain, metering, and settlement. For resource-based cities, selling the environmental value of green electricity can change the revenue structure more than generating a few hundred million kilowatt-hours more electricity.

(Source: Relevant reports from China Energy Industry Development Network; public information from Qinghai Provincial Energy Bureau; public data from State Grid Qinghai Electric Power Company)

[Research Supporting Institutions: Energy and Dual Carbon Research Center of China Industry News | China Energy Industry Development Network]

版权声明Copyright Notice

本网站摘录或转载的属于第三方的信息,目的在于传递更多信息,内容仅供参考。相关股票、投融资等资讯及分析并不代表本网站赞同其意见和对其真实性负责,不构成投资建议。

若不慎涉及侵权,请在相关内容刊发之日起 30 日内联系我们,我们将第一时间进行删除处理。

转载本网资讯请注明来源作者。本网原创文章、研究报告禁止转发。

Information excerpted or reprinted from third parties on this website is intended to convey more information for reference only. Related stocks, investment and financing news and analysis do not represent the endorsement of this website, nor does this website assume responsibility for their authenticity, and do not constitute investment advice.

If any content unintentionally infringes upon rights, please contact us within 30 days from the date of publication, and we will remove it as soon as possible.

When reprinting content from this website, please indicate the source and author. Original articles and research reports of this website may not be redistributed.

联系电话 / Tel010-85763416邮箱 / EmailEmail / Emaillsrlcyl_2026@163.com
提交留言Submit message留下联系方式,平台将把您的需求推送给匹配的产业方Leave your contact details and we will match you with relevant industry partners.

手机号与邮箱仅用于运营人员回访,提交后不在前台展示,完整信息只在后台留存。Your phone number and email are used only by our team for follow-up; they are never displayed on the site and are kept in the admin console only.

数据来源与免责声明Data Sources & Disclaimer

数据来源与口径说明:本平台数据与资讯均以「唯一官方口径」采集与发布,优先采用国家部委、国家统计局、海关总署、中国氢能联盟、IEA / IRENA / IMO 等官方或政府间机构公开数据;同一指标只取一个来源,不做多源拼接。数值为公开发布值,可能因统计口径、产地与发布时间不同而存在差异,仅供参考,不构成交易依据。Data sources and methodology: all data and news on this platform are collected and published from a single official source, giving priority to public data from government bodies and intergovernmental organisations such as the National Bureau of Statistics, the General Administration of Customs, the China Hydrogen Alliance, and IEA / IRENA / IMO. One indicator has one source only and is never stitched together from multiple sources. Figures are published values and may vary with statistical scope, origin and release date. For reference only; not a basis for transactions.

AI
智能客服Smart Assistant绿色燃料国际商务网 · 在线服务Green Fuel International Business Network · Online Service
×
人工服务:工作日 09:00—18:00 | 联系电话 010-85763416Human service: Weekdays 09:00—18:00 | Tel 010-85763416
智能客服Smart Assistant