19%与1.88公顷:一座褐煤电厂给自己留的两条后路19% and 1.88 hectares: Two exit strategies a lignite power plant left for itself

资讯详情Item Detail2026-10-07
信息来源:Source:中国能源产业发展网China Energy Industry Development Network
19%与1.88公顷:一座褐煤电厂给自己留的两条后路

高志龙

在吉林西部的八百里瀚海,一座电厂的工地上有两个数字被反复提起:19%和1.88公顷。前者是机组的最低稳燃负荷,后者是为碳捕集预留的场地面积。一个管“能不能低下来”,一个管“将来能不能减下去”——这两件事,恰好回答了新型电力系统里煤电该站在什么位置。

把这两个数字放在政策脉络里看,指向的是同一个转变:煤电的角色正从电量主体转向调节与兜底。新能源装机越多的省份,对可调节电源的需求越刚性——它既要能在用电高峰顶得上,也要能在新能源大发时压得下,还要为周边城区提供稳定的热源。白城项目的技术选择,正是围绕这三件事展开。

吉林是我国新能源开发强度较高的省份之一,省内风电、光伏装机近几年快速攀升,绿电消纳与大电网安全一度是当地能源工作的核心议题。为破解这一课题,吉林提出以绿电消纳为主线推动新能源产业价值跃迁,而煤电与新能源的互补运行,被明确为保障电网安全、提升消纳能力的支撑条件。

白城地处吉林西部,本地褐煤储量丰富,具备就近保供优势,但褐煤含水量高、热值偏低、炉膛易结焦,长期制约机组高效稳定运行。这个矛盾在新能源大发展的背景下被放大了:白城是吉林新能源开发的重点区域,风电、光伏装机规模持续扩大,而风电光伏的间歇性、波动性,需要稳定可靠的调节电源作为支撑。

项目给出的解法是三项国内首创技术。其一是打造国内首台套褐煤中速磨塔式炉,针对性攻克褐煤燃烧痛点;其二是搭载首批大功率智能永磁驱动“大小磨”系统,可随电网负荷灵活调度制粉设备,大幅降低生产能耗;其三是在60万千瓦等级机组上配置100%容量旁路系统,使机组最低稳燃负荷低至19%,宽负荷调节能力适配新能源电网的调度需求。把稳燃负荷压到19%,意味着在新能源大发、负荷低谷的时段,机组可以深度压负荷而不必频繁启停,这对电网的调节能力是实打实的增量。

灵活性的价值,最终要落到电网调度台的实际调用上。所谓最低稳燃负荷,指的是机组在不投油助燃情况下能够稳定运行的最低出力水平,这个数值越低,机组在低谷时段可下压的空间越大。对以新能源为主体的电网而言,夜间的调节能力往往比白天更紧张,19%的稳燃能力,等于给调度多留了一档可用的调节资源。

把三项首创技术串起来看,指向的都是褐煤利用这道老题:磨制与燃烧方式解决煤质适配,制粉系统调度解决能耗,旁路系统解决低负荷稳定运行。这些改进并非炫技,而是为了让本地煤能够支撑高端机组的运行参数,从燃料端降低对外调优质煤的依赖——对以本地褐煤为燃料的保供项目而言,这是经济性与可靠性的共同前提。

另一条后路写在规划图上。项目专项预留1.88公顷CCUS(碳捕集、利用与封存)专属场地,同步配套生物质、绿氨掺烧接口,厂区排污执行优于国家超低排放管控标准。据项目方介绍,项目在建设之初便规划了碳捕集系统的安装位置及管线连接点,未来可直接加装相关设备,实现对二氧化碳的捕集、运输、封存与利用。从“重发电、轻减排”到“预留降碳空间”,煤电项目的建设逻辑正在改变——不是今天不排,而是明天要有一条改的路径。

CCUS在国内电力行业的推进节奏,取决于技术成本与政策机制两条线。当前多数项目仍处于示范阶段,捕集环节的能耗与投资是主要制约。项目选择在建设之初就预留场地与管线接口,好处是不必在机组投运后再做结构性改造——未来若碳市场约束趋紧或技术成本下降,加装的门槛会低得多。

生物质与绿氨掺烧接口的意义类似。秸秆、生物质颗粒与绿氨在燃烧过程中可显著降低单位电量的碳排放,掺烧比例受锅炉特性与燃料供应限制,但接口预留让机组在燃料结构上具备了后续调整的能力。对一座设计寿命数十年的电厂来说,可升级性与当下的效率同等重要。

规模上,这是国家与吉林省双重重点保供项目。项目煤电部分投资56.98亿元,规划两台66万千瓦超超临界燃褐煤发电机组及配套设施,年发电量超40亿千瓦时,预计2028年全面投运,建成后预计年产值达20亿元。在整个近200亿元的项目盘子里,煤电板块与配套风电板块并行推进,共同支撑白城市“风光火储+绿色氢氨醇”一体化发展布局。

把项目放回吉林省的能源版图,逻辑更清楚。吉林是我国新能源开发强度较高的省份之一,绿电消纳一直是大课题。当地推进的思路是以绿电消纳为主线,做新能源产业的价值跃迁,而煤电与新能源互补运行,是保障电网安全、提升消纳能力的重要支撑。项目机组兼具深度调峰、顶峰供电和集中供热能力,建成后将显著提升吉林电网的电力供应保障能力和灵活调峰水平,缓解区域用电供需矛盾。

集中供热是这座电厂另一个容易被忽略的功能。白城冬季寒冷,城区供热负荷集中且刚性,煤电机组在发电之外承担热源角色,是北方城市普遍的现实安排。机组兼具供热能力,意味着它不仅服务电网,也直接关系居民冬季室温,这决定了它在系统中的优先级不同于纯发电机组。

从投资结构看,煤电部分56.98亿元的投资,对应两台66万千瓦机组及配套设施,单千瓦造价处于清洁高效机组的中等偏上水平,预留设施与灵活性设计是成本构成的一部分。建成后预计年产值20亿元——对地方而言,这既是能源保障项目,也是产业项目。

也需要把难度摆在桌面上。褐煤发电的经济性取决于煤价、利用小时与辅助服务收益的组合,本地褐煤就近保供是优势,但热值偏低意味着同等电量下的燃料量与厂用电更高;CCUS预留属于“未来选项”,其实际加装与运行成本,取决于碳市场政策与技术路线的成熟度。这些都不是靠一个开工节点能回答的问题。

工期本身也有变量。项目位于风沙频发、昼夜温差悬殊的吉林西部,土建浇筑、高空吊装与焊接作业都受到气候窗口的限制,施工方以抢晴天、战风天、节点必达标的节奏推进。按照规划,两台机组预计2028年全面投运,这一时间点决定了它能为“十五五”期间吉林新能源装机提供调节支撑的起始时点。

从“抢晴天、战风天,节点必达标”的施工口号,到19%的稳燃负荷与1.88公顷的预留地,这座电厂讲的是同一个故事:煤电不再是与新能源争电量的对手,而是替新能源兜底、并为自己留出减碳通道的伙伴。它能不能成为样本,要看2028年投运之后,账本上的调峰收益与减碳成本怎么算。

【研究支持机构:《中国工业报社》能源与双碳研究中心 |中国能源产业发展网】

Gao Zhilong

In the 800-li Han Sea in western Jilin, two numbers are repeatedly mentioned at the site of a power plant construction: 19% and 1.88 hectares. The former is the minimum stable combustion load of the unit, and the latter is the area reserved for carbon capture. One is about 'whether it can go lower,' the other about 'whether it can be reduced in the future'—these two issues happen to answer the question of what position coal power should occupy in a new type of power system.

Looking at these two numbers in the context of policy, they point to the same transformation: the role of coal power is shifting from being the main source of electricity to regulation and backup. Provinces with more installed renewable energy capacity have a more rigid demand for adjustable power sources—they must be able to meet peak electricity demand, curb output when renewable energy is abundant, and provide a stable heat source for surrounding cities. The technological choices of the Baicheng project are exactly built around these three tasks.

Jilin is one of the provinces in China with a relatively high intensity of renewable energy development. In recent years, the installed capacity of wind power and photovoltaics in the province has rapidly increased, and the consumption of green electricity and the safety of the large power grid have once been the core issues of local energy work. To address this issue, Jilin proposed promoting the value leap of the renewable energy industry with the consumption of green electricity as the main line, while the complementary operation of coal power and renewable energy has been clearly identified as a supporting condition to ensure grid safety and improve consumption capacity.

Baicheng, located in western Jilin, has abundant local lignite reserves and has the advantage of local supply security, but lignite has high moisture content, low calorific value, and a tendency to form slag in the furnace, which has long restricted the efficient and stable operation of units. This contradiction has been amplified against the backdrop of rapid renewable energy development: Baicheng is a key area for renewable energy development in Jilin, with a continuously expanding scale of wind power and photovoltaic installations, while the intermittency and volatility of wind and photovoltaic power require stable and reliable regulating power as support.

The solution proposed by the project consists of three domestically pioneering technologies. First, it involves the creation of the country's first set of brown coal medium-speed grinding tower furnaces, specifically addressing the pain points of brown coal combustion. Second, it is equipped with the first batch of high-power intelligent permanent magnet-driven 'large and small mill' systems, which can flexibly dispatch grinding equipment according to grid load, significantly reducing production energy consumption. Third, a 100% capacity bypass system is configured on 600,000-kilowatt units, allowing the unit's minimum stable combustion load to drop to 19%, with a wide load adjustment capability to meet the dispatching needs of a renewable energy grid. Reducing the stable combustion load to 19% means that during periods of high renewable energy output and low demand, the unit can deeply reduce its load without frequent start-stop cycles, providing tangible enhancement to the grid's regulation capability.

The value of flexibility ultimately comes down to its actual use by the power grid dispatch center. The so-called minimum stable combustion load refers to the lowest output level at which a unit can operate stably without auxiliary fuel injection. The lower this value, the more room the unit has to reduce output during off-peak periods. For a power grid dominated by renewable energy sources, nighttime adjustment capacity is often tighter than during the day. A 19% stable combustion capability equates to leaving the dispatch center an extra tier of available adjustment resources. Looking at the three pioneering technologies together, they all address the long-standing issue of lignite utilization: adjusting grinding and combustion methods to match coal quality, managing the pulverizing system to control energy consumption, and using bypass systems to ensure stable operation at low load. These improvements are not for show; they are intended to enable local coal to support the operating parameters of high-end units, reducing the reliance on externally supplied high-quality coal from the fuel side. For projects that rely on local lignite as fuel, this is a shared prerequisite for both economic efficiency and reliability.

Another backup route is marked on the planning map. The project has specially reserved 1.88 hectares of land for CCUS (carbon capture, utilization, and storage), simultaneously supporting biomass and green ammonia co-firing interfaces. The plant's wastewater discharge will comply with standards that are stricter than the national ultra-low emission control requirements. According to the project developers, from the very beginning of construction, the project planned the installation locations for the carbon capture system and the pipeline connection points. In the future, relevant equipment can be directly added to enable the capture, transport, storage, and utilization of carbon dioxide. The construction logic of coal power projects is changing from 'focusing on power generation, neglecting emission reduction' to 'reserving space for carbon reduction'—it's not about not emitting today, but about having a path to change in the future.

The pace of CCUS advancement in China’s power sector depends on two main factors: technology costs and policy mechanisms. Currently, most projects are still in the demonstration phase, with energy consumption and investment in the capture process being the main constraints. By reserving site space and pipeline interfaces at the start of construction, the project avoids the need for structural modifications after the units are in operation—if carbon market constraints tighten or technology costs decrease in the future, the threshold for adding such systems will be much lower.

The interface between biomass and green ammonia co-firing has a similar significance. Straw, biomass pellets, and green ammonia can significantly reduce carbon emissions per unit of electricity during the combustion process. The co-firing ratio is limited by boiler characteristics and fuel supply, but the reserved interface allows the plant to have the ability for subsequent adjustments in fuel structure. For a power plant with a design life of several decades, upgradability is as important as current efficiency.

In terms of scale, this is a key dual supply security project at both the national and Jilin provincial levels. The coal power part of the project involves an investment of 5.698 billion yuan, planning two 660,000-kilowatt ultra-supercritical lignite power units and supporting facilities, with an annual power generation of over 4 billion kilowatt-hours. It is expected to be fully operational by 2028, and once built, the expected annual output value will reach 2 billion yuan. Within the nearly 20 billion yuan project portfolio, the coal power segment and the supporting wind power segment are advancing concurrently, jointly supporting Baicheng City's integrated development layout of 'wind, solar, thermal, storage, and green hydrogen, ammonia, and methanol.'

Placing the project back into Jilin Province's energy landscape makes the logic clearer. Jilin is one of China's provinces with relatively high intensity in renewable energy development, and the consumption of green electricity has always been a major challenge. The local approach is to focus on green electricity consumption as the main line and achieve value upgrading in the renewable energy industry, while the complementary operation of coal and renewable energy is an important support for ensuring grid safety and improving consumption capacity. The project units possess deep peak regulation, peak power supply, and centralized heating capabilities. Once completed, they will significantly enhance Jilin's grid power supply security and flexible peak regulation capability, alleviating regional electricity supply and demand conflicts.

Centralized heating is another function of this power plant that is easily overlooked. Baicheng experiences cold winters, with concentrated and rigid demand for urban heating. Coal power units not only generate electricity but also serve as a heat source, which is a common arrangement in northern cities. The units having the heating capability means they not only serve the grid but also directly affect residents' indoor temperatures in winter, which determines their priority in the system differently from pure power generation units.

From the perspective of investment structure, the 5.698 billion yuan investment in the coal power sector corresponds to two 660,000-kilowatt units and supporting facilities. The cost per kilowatt is at the higher-middle level for clean and efficient units, with reserved facilities and flexible design accounting for part of the cost. Once completed, it is expected to generate an annual output value of 2 billion yuan — for the local area, this is both an energy security project and an industrial project.

It is also necessary to lay the challenges on the table. The economic viability of lignite power generation depends on a combination of coal prices, utilization hours, and auxiliary service revenue. The local supply of lignite nearby is an advantage, but its low calorific value means higher fuel consumption and own-use power for the same amount of electricity. CCUS reservation is regarded as a “future option,” and the actual cost of installation and operation depends on the maturity of carbon market policies and technological pathways. These are not questions that can be answered by a single commencement milestone.

The construction period itself also has variables. The project is located in western Jilin, an area prone to sandstorms and extreme temperature differences between day and night. Civil construction pouring, high-altitude hoisting, and welding operations are all constrained by climate windows. The construction team is advancing with the rhythm of seizing sunny days, battling windy days, and meeting critical milestones. According to the plan, the two units are expected to be fully operational in 2028. This timing determines the starting point at which they can provide adjustment support for Jilin's renewable energy installations during the 15th Five-Year Plan period.

From the construction slogan 'seize sunny days, battle windy days, ensure milestones,' to a stable fuel load of 19% and 1.88 hectares of reserved land, the power plant tells the same story: coal power is no longer a competitor for electricity with renewable energy, but a partner that underpins renewable energy and leaves a pathway for its own carbon reduction. Whether it can become a benchmark depends on how the peak-shaving revenue and carbon reduction costs are calculated after it goes into operation in 2028.

Sources: Xinhuanet, Economic Daily, Jilin Provincial Development and Reform Commission website, Xinhua Finance, and publicly available information from the project party

[Research support institutions: Energy and Carbon Neutrality Research Center, China Industrial Newspaper | China Energy Industry Development Network]

版权声明Copyright Notice

本网站摘录或转载的属于第三方的信息,目的在于传递更多信息,内容仅供参考。相关股票、投融资等资讯及分析并不代表本网站赞同其意见和对其真实性负责,不构成投资建议。

若不慎涉及侵权,请在相关内容刊发之日起 30 日内联系我们,我们将第一时间进行删除处理。

转载本网资讯请注明来源作者。本网原创文章、研究报告禁止转发。

Information excerpted or reprinted from third parties on this website is intended to convey more information for reference only. Related stocks, investment and financing news and analysis do not represent the endorsement of this website, nor does this website assume responsibility for their authenticity, and do not constitute investment advice.

If any content unintentionally infringes upon rights, please contact us within 30 days from the date of publication, and we will remove it as soon as possible.

When reprinting content from this website, please indicate the source and author. Original articles and research reports of this website may not be redistributed.

联系电话 / Tel010-85763416邮箱 / EmailEmail / Emaillsrlcyl_2026@163.com
提交留言Submit message留下联系方式,平台将把您的需求推送给匹配的产业方Leave your contact details and we will match you with relevant industry partners.

手机号与邮箱仅用于运营人员回访,提交后不在前台展示,完整信息只在后台留存。Your phone number and email are used only by our team for follow-up; they are never displayed on the site and are kept in the admin console only.

数据来源与免责声明Data Sources & Disclaimer

数据来源与口径说明:本平台数据与资讯均以「唯一官方口径」采集与发布,优先采用国家部委、国家统计局、海关总署、中国氢能联盟、IEA / IRENA / IMO 等官方或政府间机构公开数据;同一指标只取一个来源,不做多源拼接。数值为公开发布值,可能因统计口径、产地与发布时间不同而存在差异,仅供参考,不构成交易依据。Data sources and methodology: all data and news on this platform are collected and published from a single official source, giving priority to public data from government bodies and intergovernmental organisations such as the National Bureau of Statistics, the General Administration of Customs, the China Hydrogen Alliance, and IEA / IRENA / IMO. One indicator has one source only and is never stitched together from multiple sources. Figures are published values and may vary with statistical scope, origin and release date. For reference only; not a basis for transactions.

AI
智能客服Smart Assistant绿色燃料国际商务网 · 在线服务Green Fuel International Business Network · Online Service
×
人工服务:工作日 09:00—18:00 | 联系电话 010-85763416Human service: Weekdays 09:00—18:00 | Tel 010-85763416
智能客服Smart Assistant